layout: post
|
||||
title: "Reclaiming Story Points"
|
||||
tags:
|
||||
- featured
|
||||
- agile
|
||||
team: Technical Project Management
|
||||
author: lbuschbaum
|
||||
---
|
||||
|
||||
Scribd has been in an agile transition for two years now and as we iterate and
|
||||
improve with company growth we have needed to reevaluate a number of practices
|
||||
such as utilizing **story points**.
|
||||
|
||||
[Story points](https://agilefaq.wordpress.com/2007/11/13/what-is-a-story-point/) in agile are a way of estimating how much work something is. They
|
||||
are deliberately _not_ exact functions of difficulty and time because you never
|
||||
know all the complications when you start a project. Even something as simple
|
||||
as making dinner can get tripped up by a missing ingredient or a dirty pot, so
|
||||
too can software delivery. The issue that we ran into is that we rolled it out with an
|
||||
early set of folks who were clear on it and how to use it but we didn't
|
||||
socialize that change both across the organization and upwards.
|
||||
|
||||
It's very easy to say 'that's 8 points' and hard to translate that out into a
|
||||
meeting where we cover all the projects in flight with a target and actual done
|
||||
date attached to it. Business gets attached to those dates and makes plans
|
||||
using them and then a team comes back with a slip and suddenly everyone is
|
||||
upset. The team is upset because they knew that 8 points was an estimate that
|
||||
accommodated a period of time in which they could deliver. Management is upset
|
||||
because things slipped and now they feel things are late when that was never
|
||||
really going to be the time anyway.
|
||||
|
||||
<center>
|
||||
<img src="/post-images/2020-03-story-points/stop.png" alt="Stop!" align="center"/>
|
||||
(<em><a href="https://publicdomainvectors.org/en/free-clipart/Stop-speech-bubble/82516.html" target="_blank">source</a></em>)
|
||||
</center>
|
||||
|
||||
So story points got banned from the management meeting. Project managers could
|
||||
now only speak to deadline dates and added language that mentioned things like
|
||||
'best estimate' and 'could slip' to hedge around the fact that software
|
||||
development isn't an exact science as much as we would like it to be. We still
|
||||
talked about them and used them in the team meetings but it was a verboten term
|
||||
outside that space which led to its own tensions.
|
||||
|
||||
One of the related reasons story points got banned was the nature of the
|
||||
imprecision. Yes, points should be specific to the team but our velocity was
|
||||
completely unpredictable from team to team. Sometimes it would be 20 points and
|
||||
others 50. Regression passes were sometimes included and pointed, sometimes
|
||||
they weren't. It started with a team of more junior developers and QA that had
|
||||
one of the aforementioned velocity issues. We asked them how big a 3/5/8 was
|
||||
and got a different answer from each of them. We had found the underlying
|
||||
problem that had given story points a bad name.
|
||||
|
||||
It was time to go back to basics. We had a story pointing workshop with that
|
||||
team that already had strong communication and was a safe space to talk through
|
||||
in the retrospectives why they were all over the map. Some of it was because
|
||||
they were more junior and were less likely to know where the problems were in
|
||||
the code base but some of it was because we had just assumed that everyone knew
|
||||
what a 5 might entail. An hour later we had a white-board covered in notes with
|
||||
items under each number in the Fibonnaci sequence. Items that included things
|
||||
from each of the developers, QA and the chapter lead (in this case a senior
|
||||
technical developer). We did it again with the entire mobile QA team, sharing
|
||||
some of the findings after we first did the brainstorm fresh, sharing where
|
||||
that team had seen points falling. It turned into a wiki page that was shared
|
||||
within the project management team and spread from there.
|
||||
|
||||
<center>
|
||||
<img src="/post-images/2020-03-story-points/efforts.png" alt="Different efforts are different!" align="center"/>
|
||||
(<em><a href="https://www.slideshare.net/arkanaan/agile-relative-sizing-v2" target="_blank">source</a></em>)
|
||||
</center>
|
||||
|
||||
We were clear throughout this process that points were still team specific and
|
||||
that none of this was to be taken as hard and fast rules but it gave teams a
|
||||
place in which to start the conversation and have common ground. We don't want
|
||||
to make it sound like all the teams were terrible at pointing or having
|
||||
reliable velocity but the variability often exceeded 10% which made it hard for
|
||||
management to show trust in our date estimates. It became easier for teams to
|
||||
have more accuracy which led to more trust in deadlines which in turn led to a
|
||||
way where we could talk about story points again.
|
||||
|
||||
When the deadlines shifted to being reliable within a day or two it was less
|
||||
charged of a conversation to mention that we'd done a good breakdown on the
|
||||
work and it was reflected in Jira that way. We do a project lifecycle that
|
||||
starts with a product brief, goes through design iterations, and then goes into
|
||||
story breakdown and sizing. Only after those steps are done do we 'put hands on
|
||||
keyboard' and start writing software. It turns out people really do need time
|
||||
to think through the problem before solving it. Again, this isn't perfect. We
|
||||
still have tech debt and brittle code. We will always have people who under or
|
||||
over estimate work - which is why we use points.
|
||||
|
||||
With bringing in words like velocity and showing that over time teams were
|
||||
getting more reliable in their estimates we were able to show management that
|
||||
the method was worth trusting and we were again able to use the term story
|
||||
points in our meetings with them. The reaction to the phrase early on was
|
||||
justifiable from the point of view and what we did to fix the underlying issue
|
||||
led to us being able to reclaim it.
|